127th Street, Black Bob to Pflumm

Project Number: 30401C

Project Location/Limits:
On 127th Street between Black Bob Road and Pflumm Road.

Project Scope:
The existing two lane street will be expanded to an arterial with 2 lanes in each direction. For more information, please see www.improve127th.com

Current Project Status:
Pyramid Contractors was awarded the construction of the project in April of 2013.  Construction is underway.  The first phase of the project is from Black Bob Road to the Olathe East High School entrance is substantially complete and has been opened to traffic one lane in either direction. 

 
The second phase of the project extends from the Olathe East Entrance to Hallet Street.  This phase is on schedule to be opened to traffic by early December, weather permitting.
 
The next phase of the project will include the reconstruction of the two concrete structures between Gallery and Rene.  The section of 127th Street between Gallery and Rene will be closed through the winter. 
 
Road closure will occur for the duration of the project and detours are provided.
 
The project is tentatively scheduled to be complete in August of 2014. 

Get more information at the www.improve127th.com website.

Total Project Cost: $17,839,053

 

For more information regarding this project: